Dead in the Water? Requested Subsidy for Surf City Desal Project Stirs Debate

John Earl
Surf City Voice
07/07/2011

What is the future of seawater desalination in California?

As of 2006, 22 desalination plants had been proposed for construction along the California coast between San Rafael in the north to Carlsbad in the south. Today, only nine projects are still in the running, and even those are on shaky ground, according to an analysis by the Desal Response Group, a statewide organization generally opposed to ocean desalination.

Critics of ocean desalination (desal) say that the water industry’s dream — shared with evangelical zeal by a growing cabal of public water officials — of sprinkling the coast with desalination plants is dead in the water.

As proof, they point to spiraling costs, lack of financing, stalled technology, and higher than average water supplies after the end of the California “drought.” They say that there are underutilized and much more cost-efficient alternatives such as conservation, increased water collection and waste water recycling – minus seawater desal’s high environmental costs.

That’s why desal critics are upset after a June 6 vote by the Municipal Water District of Orange County (MWDOC) to send a letter to its umbrella agency, the Metropolitan Water District of Los Angeles County (MET), to request $350 million in funding support for the Huntington Beach Desalination Project that Poseidon Resources Inc. wants to build on Pacific Coast Highway and Newland Avenue.

At an estimated construction cost of $700 (according to a recent Costal Commission analysis), the plant would produce 50 million gallons a day or 56,000 acre feet per year of drinking water, 8 percent of Orange County’s supply. The plant would share the seawater intake pipes currently used for cooling by the AES power generating plant.

Poseidon wants to build a nearly identical desal plant in Carlsbad in San Diego County.

The proposed taxpayer-funded subsidy, says the letter, which was written June 23 and obtained by the Voice, would help MWDOC’s agencies to “defray” the high cost of desalinated water—which is generally two to four times higher than other sources.

The subsidy would go through MWDOC’s agencies which would in turn pay it directly to Poseidon over 25 years at $14 million per year in return for water delivered.

Largely funded by taxpayers outside of Orange County who won’t use the water, the subsidy would artificially lower the cost of Poseidon’s desalinated water, which would still probably not be competitive with the cost of water from other sources, including imported water. Desal advocates say that technological improvements for desalination and rising costs of imported water will cause prices to crisscross in the near future, but those improvements show no signs of arriving soon, if ever.

A pro-industry report published in 2004 by the federal government concluded that the invention of cost effective desal technology would require a huge influx of government subsidies to fund the research and development that the industry is lax in doing itself. Even then, it would take over 20 years to make seawater desal competitive, the report estimated.

Without huge public subsidies, Poseidon cannot attract the private investors and get permission to pass tax free bonds also needed to finance the construction of its Huntington Beach plant. To the point, without subsidies—and based on past experience $350 million would not be nearly enough—Poseidon’s HB plant will be out of business.

That is exactly the scenario that played out last year for Poseidon’s proposed desalination plant at Carlsbad in San Diego County. It would be nearly identical in size and type and has received all of the necessary permits but stalled due to lack of financing and increased cost projections for the price of its water.

As reported last June by the Voice, a memo from the city manager Peter A. Weiss of Oceanside, one of nine water San Diego County agencies that had signed water purchasing agreements with Poseidon at that time, pointed out that Poseidon would need $630 million in government financial assistance.

Read Full Article